Project Management is an agent skill for AI coding assistants (Claude Code, OpenClaw, Cursor, Codex). End-to-end software project management: charter, throughput-based sprint planning, OKRs, RAID logs, ADR/DACI decisions, dependency contracts, release gates, retros. Use when planning a project/sprint, scoping/estimating, running ceremonies, tracking risks/dependencies, writing status updates, or picking Jira/Linear/GitHub Projects. Install with: npx skills-ws install project-management.

operationsv1.0.0Updated
copied ✓
openclawclaude-codecursorcodex
0 installsSecurity scan: cleanSource code

Project Management

Sprint Planning

Capacity-Calibrated Planning (not a velocity formula)

Velocity is team-specific and emergent — do not derive a per-person-day rate and multiply it back up. A person-days × focus-factor formula gives false precision and invites "weaponized velocity" (see Anti-Patterns). Instead, calibrate each sprint against the team's own recent history and adjust for what's actually different this sprint:

  1. Baseline from history. Take the last 3–6 sprints of completed work. Track throughput (items finished/sprint) alongside, or instead of, story points — throughput is harder to game and works even with no-estimate teams. Use the range (e.g. 28–41 pts, or 9–14 stories), not just the mean.
  2. Adjust for capacity deltas. Scale the baseline by known changes only: PTO/holidays, on-call rotation, ramping new hires (count at ~50% for the first 2–3 sprints), planned support/KTLO load. A simple ratio works: target = baseline × (available person-days this sprint / typical person-days).
  3. Reserve an explicit buffer for unplanned work (incidents, escaped bugs, urgent asks). Make it visible — e.g. hold back 15–25% of capacity, or carry a named "unplanned" swimlane — rather than over-committing and silently absorbing it.
  4. Commit to a confidence range, not a single number. Pull stories until you reach the low end of your throughput range with high confidence; mark the next 1–2 as "stretch." Carryover, dependencies, and uncertainty live here, not in a fixed cap.

There is no universal "never exceed X%" rule. A stable team with a clean sprint can pull stretch items; a team with carryover, new joiners, or heavy on-call should commit below its average. Let the historical range and the capacity deltas decide.

Estimation Techniques

TechniqueBest ForScale
T-shirt sizingEpics, roadmap itemsXS, S, M, L, XL
Planning pokerSprint storiesFibonacci: 1,2,3,5,8,13,21
Three-pointRisky/uncertain work(O + 4M + P) / 6

Rule: If estimate > 13 points, decompose. If team variance > 2 Fibonacci steps, discuss.

OKR Framework

Structure

Objective: Qualitative, inspiring, time-bound
  └─ Key Result 1: Measurable OUTCOME, not an output/task
       └─ Initiative: Concrete project/task driving the KR
  └─ Key Result 2: ...
  └─ Key Result 3: (max 3-5 KRs per objective)

KRs must be outcomes ("reduce p95 checkout latency to <400ms", "lift activation rate 22%→30%"), never shipped-features ("launch new checkout"). A feature you can mark "done" is an initiative; the outcome it moves is the KR. Output-only OKRs are the most common failure mode (see Anti-Patterns).

Scoring & Cadence

The classic Google 0.0–1.0 grade is one model; pick the one that drives the conversation you want:

ModelWhen to useHow it reads
0.0–1.0 gradeStretch/aspirational goals0.0–0.3 no progress · 0.4–0.6 progress, missed · 0.7–1.0 delivered (0.7 = "healthy ambitious")
Confidence %Continuous/weekly planningEach KR carries a live "% likely to hit" updated at check-in; trend matters more than the absolute
RAG / status healthExec & portfolio reportingOn-track (green) / at-risk (amber) / off-track (red) + a one-line "why" — fast to scan, forces a narrative
Outcome healthAlways-on metrics (NPS, uptime, retention)Track the metric itself vs. target band; no quarter-end "grade," just current state

Many 2026 orgs run confidence + RAG continuously and drop the formal end-of-quarter grade. Whichever you choose: score the KR, never the initiative, and don't tie bonuses to scores (it kills ambition and breeds sandbagging).

  • Weekly: 15-min check-in — update confidence/RAG, surface blockers, re-prioritise initiatives
  • Monthly: Review trajectory, kill or double-down on initiatives
  • Quarterly: Retrospect on OKRs (not just grade them), set next cycle

Stakeholder Management

RACI Matrix

TaskPMEng LeadDesignExec
RequirementsACRI
ArchitectureCRII
Launch decisionRCCA

R=Responsible, A=Accountable (one per row), C=Consulted, I=Informed.

Communication Plan

AudienceFrequencyFormatContent
Exec sponsorsBiweeklyEmail/slidesStatus, risks, decisions needed
Cross-team depsWeeklySync/SlackBlockers, timeline updates
TeamDailyStandupYesterday/today/blockers

Status Update Template

Lead with the verdict, not the activity log. Execs scan the RAG line and the asks; everything else is backup. Keep it to a screen.

**<Project> — week of <date>**   Overall: 🟢 On track | 🟡 At risk | 🔴 Off track
Why: <one line — the single most important fact this week>

📈 Progress:  <2–4 outcomes/milestones shipped, in metrics where possible>
🎯 Next:      <what lands by next update>
⚠️ Risks/blockers: <top 1–3, each with owner + what you're doing>
🙋 Decisions/help needed: <explicit asks — who must do what, by when>
🗓️ Timeline:  On track for <milestone @ date> | Slipped to <date> because <reason>

Rules: the RAG status is honest, not green-by-default; never let a status go red for the first time on the deadline (escalate ≥2 sprints early). State asks as actions with an owner and a date, not vague concerns. Outcomes ("activation 24%→27%") beat activity ("worked on onboarding").

Agile Ceremonies

CeremonyDurationCadenceOutput
Standup15 minDailyBlockers surfaced
Sprint Planning1-2 hrPer sprintCommitted backlog
Sprint Review/Demo1 hrPer sprintStakeholder feedback
Retrospective1 hrPer sprintAction items (max 3)
Backlog Refinement1 hrWeeklyEstimated, ready stories

Kanban Workflow

Backlog → Ready → In Progress → Review → Done
          (cap)    (WIP cap)    (WIP cap)

The four flow metrics (per Kanban Guide, v2025.5):

  • WIP: items started but not finished. The lever you control directly.
  • Cycle time: In Progress → Done, per item. Optimise this; report the distribution (e.g. 50th/85th percentile), not just the average.
  • Work item age: how long an in-flight item has been open — the single most actionable signal. Items aging past your 85th-percentile cycle time get pulled into focus first.
  • Throughput: items finished per week. Use its recent range for forecasting (see Sprint Planning).

Setting WIP limits — measure, don't guess. There is no formula like (team/2)+1; an arbitrary cap can starve or flood the board depending on item size and handoffs. Instead:

  1. Start by capping the most contended stage (usually Review/code-review or QA, where work piles up), not every column.
  2. Make the team's current in-flight count the starting limit, then ratchet down until cycle time drops and aging items shrink — lower WIP almost always speeds flow.
  3. Give "Ready" a small buffer cap (e.g. one sprint's worth of refined work) so the backlog stays groomed without hoarding.
  4. Add classes of service when needed — Expedite (1 lane, pre-empts), Standard (FIFO), Fixed-date (deadline), Intangible (KTLO) — so urgent work doesn't blow up every limit ad hoc.

Risk Management

Probability × Impact Matrix

Low ImpactMed ImpactHigh Impact
High ProbMediumHighCritical
Med ProbLowMediumHigh
Low ProbLowLowMedium

For each High/Critical risk, document: Risk → Trigger → Mitigation → Owner → Status

RAID Log

The single source of truth for everything that can derail delivery. One living table (or one tab each) reviewed weekly; every item has a named owner and a next review date. RAID = Risks, Assumptions, Issues, Dependencies.

TypeWhat it capturesKey columns
RiskMight happen, would hurtDescription · Prob×Impact · Trigger · Mitigation · Owner · Status
AssumptionBelieved true but unverified; becomes a risk if falseAssumption · Validates by (date) · Impact if wrong · Owner
IssueAlready happening, needs action nowDescription · Severity · Action · Owner · Due · Status
DependencyNeeds something from elsewhere (see Dependency Contracts)What · Direction (in/out) · Owner · Needed-by · Status
## RAID — <Project>   (reviewed weekly, last: <date>)
### Risks
| ID | Risk | P×I | Trigger | Mitigation | Owner | Status |
|----|------|-----|---------|------------|-------|--------|
| R1 | Vendor API rate limits block launch traffic | High | >80% quota in load test | Negotiate quota + cache layer | @lead | Open |
### Assumptions
| ID | Assumption | Validate by | If wrong | Owner |
|----|------------|-------------|----------|-------|
| A1 | Legacy data is clean enough to migrate as-is | M1 + 1wk | +2 sprints for ETL cleanup | @data |
### Issues
| ID | Issue | Sev | Action | Owner | Due | Status |
|----|-------|-----|--------|-------|-----|--------|
| I1 | Staging env down, blocking QA | High | Rebuild from IaC | @devops | Today | In progress |
### Dependencies → tracked in Dependency Contracts table

Promote assumptions early. An untested assumption is a hidden risk; the most common project failure is discovering a load-bearing assumption was false at the worst possible moment. Validate the riskiest ones in discovery.

Decision Log (ADR / DACI)

Capture why, not just what — the rationale is the asset future-you and new joiners need. Two complementary tools:

  • DACI decides: Driver (drives to a decision), Approver (one person who signs off), Contributors (consulted), Informed. Use it to assign decision rights on the charter so decisions don't stall.
  • ADR (Architecture/Any Decision Record) records the outcome. One short Markdown file per significant decision, committed next to the code, numbered and immutable (supersede, never edit).
# ADR-007: Use server-side sessions instead of JWT
Date: 2026-06-07   Status: Accepted   (Proposed | Accepted | Superseded by ADR-NNN)
Driver: @lead   Approver: @eng-director   Deciders: @backend, @security

## Context
What forces this decision now? Constraints, requirements, the problem.

## Options considered
1. Stateless JWT — pros / cons
2. Server-side sessions (Redis) — pros / cons   ← chosen
3. ...

## Decision
We will <X> because <the trade-off we are accepting>.

## Consequences
Positive: <…>   Negative / cost: <…>   Follow-ups: <ADRs/tickets this spawns>

Log a decision when it's expensive to reverse, affects multiple teams, or someone will ask "why did we do it this way?" in six months. Trivial/reversible (two-way-door) decisions don't need an ADR — decide fast and move on.

Change Requests & Scope Control

Scope creep is silent; a lightweight change-control step makes it visible and owned. The charter's In/Out scope is the baseline — anything that moves the baseline (scope, date, budget, or a frozen dependency contract) is a change request, not a quiet edit.

# CR-014: Add SSO to launch scope
Requested by: <name>   Date: <YYYY-MM-DD>   Status: Proposed
What changes: Add SAML SSO to the GA scope (was Out-of-scope in charter).
Why / value: Unblocks 3 enterprise deals (~$Xk ARR).
Impact:  Schedule: +1 sprint  ·  Scope: −1 stretch story  ·  Risk: new IdP dependency (→ RAID R4)
Options: (a) Add now, slip GA 1 sprint  (b) Ship GA, SSO as fast-follow  (c) Decline
Decision (Approver = sponsor): ____   Date: ____

Rule: small estimate tweaks within scope are normal sprint hygiene — don't CR them. Reserve CRs for changes to the committed baseline. Every accepted CR updates the charter, the plan, and (if relevant) the dependency contract.

Discovery → Delivery Handoff

A story is only "Ready" when the team can build it without guessing. Gate the backlog on a Definition of Ready and hold acceptance criteria to a quality bar.

Definition of Ready (DoR) — a story enters a sprint only if:

  • User-valued and independently shippable (INVEST); vertical slice, not a layer
  • Acceptance criteria written and testable
  • Designs/API contracts attached or explicitly N/A
  • Dependencies identified (→ Dependency Contracts) and not blocking
  • Sized; if > 13 pts or > ~3 days, split it
  • No open questions that block starting

Acceptance-criteria quality bar. Prefer Given/When/Then (Gherkin) for behaviour; cover the happy path and the obvious edge/error cases; make each criterion observable (a tester can pass/fail it without reading the code). Bad: "login works." Good:

Given a registered user with a valid password
When they submit the login form
Then they land on /dashboard and a session cookie is set
And after 5 failed attempts the account is locked for 15 min  # error path

Definition of Done (DoD) — team-wide, not per-story: code reviewed, tests passing in CI, acceptance criteria met, docs/changelog updated, feature-flagged if risky, deployed to staging, observability (logs/metrics/alerts) in place. "Done" means releasable, not "works on my machine."

Release Gates & Readiness

Don't decide "ship?" in the launch meeting. Define gates up front; each is a checklist with a named owner who signs off.

Release readiness checklist:

  • All committed scope done (DoD met) or explicitly de-scoped via CR
  • Acceptance criteria verified; no open Sev-1/Sev-2 bugs
  • Rollout plan: canary/phased %, success metrics, rollback steps tested (not just written)
  • Feature flags wired; kill-switch verified in staging
  • Observability: dashboards, alerts, and on-call owner for launch window
  • Load/perf validated against the guardrail metric (e.g. p95 budget)
  • Security/privacy review done (authz, PII, secrets); compliance sign-off if regulated
  • Data migrations reversible / backed up; dry-run on prod-like data
  • Docs, support runbook, and customer comms ready
  • Go/No-Go: each gate owner gives an explicit go; sponsor approves

Post-launch: watch the success + guardrail metrics through the rollout; keep the on-call owner engaged; schedule a blameless review (below) within a week — for incidents and clean launches.

Project Charter

The one-page contract that aligns everyone before work starts. Write it, get the sponsor to sign off, link it from the tracker. Keep it to a page.

# <Project name> — Charter
Sponsor: <single exec who owns the outcome & budget>
Lead / DRI: <single accountable owner>   Date: <YYYY-MM-DD>   Status: Draft

## Problem & why now
<1–3 sentences: the problem, who has it, the cost of not solving it.>

## Outcome / success metrics
- <Measurable outcome, e.g. "checkout conversion +3pp by Q4">
- <Guardrail metric that must NOT regress, e.g. "p95 latency stays <400ms">

## Scope
In:  <bullets — what we ARE doing>
Out: <bullets — explicitly NOT doing, to kill scope creep early>

## Milestones (target, not commitment until planned)
- M1 Discovery complete — <date>
- M2 Beta / first usable slice — <date>
- M3 GA / launch — <date>

## Budget / team       Key risks & assumptions      Decision rights
<headcount, $, infra>  <top 3, link RAID log>       <DACI: see Decision Log>

Kickoff Checklist

  • Charter written and signed off by the sponsor
  • Single accountable owner (DRI) named — exactly one
  • Problem statement + success metrics (incl. guardrails) defined
  • Stakeholders identified (RACI complete)
  • Scope documented (in-scope / out-of-scope)
  • Timeline with milestones
  • Dependencies mapped with owners and dates (see Dependency Contracts)
  • RAID log started (Risks, Assumptions, Issues, Dependencies)
  • Communication plan agreed
  • Tech approach reviewed; key decisions captured as ADRs

Post-Mortem / Retrospective

Blameless Post-Mortem Template

  1. Summary: What happened, impact, duration
  2. Timeline: Chronological events with timestamps
  3. Root cause: Use 5 Whys (ask "why" iteratively until systemic cause found)
  4. Contributing factors: Process gaps, tooling issues
  5. Action items: Each with owner and deadline
  6. Lessons learned: What went well, what didn't

5 Whys Example

Why did the deploy fail? → Config was wrong
Why was config wrong? → Manual edit in prod
Why manual edit? → No automated config management
Why no automation? → Never prioritized
Why? → No visibility into config-related incidents
→ Action: Implement config-as-code with PR review

Dependency Contracts

A tracking table isn't enough — a cross-team dependency needs an explicit contract both sides agree to, or it slips silently. For each one, pin down: what (the interface/deliverable), owner (a named person, not a team), date (committed, not "soon"), acceptance (how you'll know it's done/correct), and a fallback if it's late.

DependencyOwner (named)Interface / contractCommitted byAcceptanceFallback if lateStatus
Auth API v2@platform-leadOpenAPI spec frozen + staging endpointSprint 5 startContract tests green in our CIKeep v1 behind flag, ship without SSOIn progress
Design system update@design-leadFigma tokens + published componentsSprint 4Components in StorybookInline one-off styles, refactor laterAt risk

Rules of thumb:

  • Freeze the interface contract (API schema, event payload, component props) before both teams build against it; track schema/contract changes as change requests.
  • Prefer contract tests / mocks so your team can build against the agreed interface before the dependency is real — decoupling delivery from the other team's timeline.
  • Escalate any at-risk dependency ≥2 sprints before its needed date, via the sponsor and the at-risk owner's manager — don't wait for it to be blocked.
  • Every dependency also lives in the RAID log (D); the contract table is the working detail.

Burndown Charts

  • Burndown: Remaining work vs. time (scope creep = line goes up)
  • Burnup: Completed work + total scope vs. time (shows scope changes explicitly)

Use burnup for stakeholder reporting (makes scope changes visible).

Anti-Patterns

Anti-patternWhy it bitesDo instead
Weaponized velocityVelocity becomes a productivity target → estimate inflation, gaming, burnout; it's a planning signal, not a KPIForecast with throughput ranges; never compare teams or report velocity to execs as performance
Output-only OKRsKRs that are shipped features ("launch X") can be "done" while moving no metric — busywork dressed as strategyEvery KR is an outcome; features are initiatives under it
Too many WIP states / no limitsLong pipelines hide where work stalls; everything "in progress," nothing finishingFew columns, cap the contended stage, watch work-item age
No single accountable ownerShared accountability = no accountability; decisions stall, blame diffusesExactly one DRI per project, one Approver (A) per decision/row
Retro theatreSame issues every sprint, no change → cynicism, retros get skipped≤3 action items, each with owner + due date; review last retro's actions first
Scope creep by silenceUntracked "small" additions blow the date with no decision trailCharter In/Out baseline + change requests for baseline changes
Status by activity"We worked hard on X" hides whether the outcome is at riskLead with RAG + outcome metrics + explicit asks
Estimate as commitmentTreating a forecast as a promise punishes uncertainty, breeds padding and sandbaggingCommit to a confidence range; protect with an unplanned-work buffer
Dependency by hope"They said it'd be ready" with no contract → silent slipFrozen interface contract + named owner + dated commitment + fallback

Context Adaptations

Hybrid Scrum / Kanban (Scrumban). Common in 2026 for teams with mixed planned + interrupt-driven work. Keep sprint planning + retro for rhythm and stakeholder cadence, but run the board with WIP limits and flow metrics instead of a rigid commitment. Add an Expedite lane for interrupts so they don't blow the sprint.

Remote / distributed / async. Default to written + async: a decision log and status doc beat a meeting nobody remembers. Replace daily standup with an async written check-in; reserve synchronous time for decisions and unblocking, not status. Be explicit about time-zone overlap windows; capture every meaningful decision as an ADR so people across zones aren't blocked waiting to ask.

Regulated / safety-critical (fintech, health, gov). Add explicit compliance/security gates to release readiness; keep an audit trail (immutable decision log, signed approvals, change requests) — auditors will ask "who approved this and when?" Map controls (SOC 2 / ISO 27001 / HIPAA / GDPR / PCI as applicable) to release gates; never let "move fast" skip a required sign-off. This is operational guidance, not legal advice — confirm specific obligations with compliance/legal counsel.

Tooling (mid-2026)

Pick tools that make the artifacts above live, not screenshots in a doc. Capabilities and pricing change often — verify current plans/limits at each vendor's pricing page before standardizing.

ToolSweet spotNotes
LinearFast-moving product/eng teamsOpinionated, keyboard-first; cycles ≈ sprints, Projects/Initiatives for roadmap; strong GitHub/Slack sync
Jira + Jira Product Discovery (JPD)Larger/regulated orgs needing process + audit trailJPD handles idea/opportunity prioritization → feeds delivery in Jira; heavy but governable
GitHub ProjectsTeams living in GitHubIssues/PRs as the source of truth; custom fields, roadmap/board views, automation via built-in workflows + Actions
Asana / NotionCross-functional & ops-heavy programsNotion = charter/RAID/ADR docs + lightweight DB; Asana = structured tasks + rules/automation for status roll-ups

AI-assisted tracking (use, but verify): AI meeting notetakers can auto-draft action items, decisions, and owners — pipe them straight into the decision log and tracker. LLM assistants in Linear/Jira/Notion can draft status updates from board state, summarize a sprint, triage/dedupe incoming issues, and surface stale work-items. Always have a human verify owners, dates, and the RAG call before anything goes to stakeholders — an AI summary that quietly mislabels a red project as green is worse than no summary.

Cross-skill: for competitive/market inputs that feed a charter's "why now" or OKR targets, see the competitor-intelligence skill.